Rare 5 |
Unlikely 4 |
Possible 3 |
Likely 2 |
Almost Certain 1 |
Low | Manage and monitor at the project manager level |
Medium | Actively manage / monitor at the Sector Head and Project Steering Committee |
High | Requires an appropriate treatment and response at the Project Steering Committee, and Executive Management and Risk Committee (EMRC) level with progress reporting to the Secretary General |
LIKELIHOOD | Timeframe | Probability % |
---|---|---|
Rare (1) | The risk is expected to occur once in 5 years or more | < 20% |
Unlikely (2) | The risk is expected to occur once in 4 years | > 20% and < 40% |
Possible (3) | The risk is expected to occur once in 3 years | > 40% and < 60% |
Likely (4) | The risk is expected to occur once in 2 years | > 60% and < 80% |
Almost Certain (5) | The risk is expected to occur once or more per year | > 80% |
IMPACT | Description |
---|---|
Negligible (1) | Little or no impact on achieving outcome objects |
Minor (2) | Minor impact on achieving desired results to the extent that one or more stated outcome objectives will fall below goals but well above minimum acceptable levels |
Moderate (3) | Moderate impact on achieving desired results to the extent that one or more stated outcome objectives will fall well below goals but above minimum acceptable levels |
Major (4) | Significant impact on achieving desired results to the extent that one or more stated outcome objectives will fall below acceptable levels |
Extreme (5) | Severe impact on achieving desired results to the extent that one or more of its critical outcome objectives will not be achieved |